Wiring Jacobhouse, Day 4.
3/24/19: Building Summary: Today I started off by going onto Youtube and finding the method I thought best for stripping […]
Wiring Jacobhouse, Day 4. Read More »
3/24/19: Building Summary: Today I started off by going onto Youtube and finding the method I thought best for stripping […]
Wiring Jacobhouse, Day 4. Read More »
3/23/19: Building Summary: Today I went down to Jacobhouse at 9:30 AM*. There, I soon found out that Alan Hendrickson
Wiring Jacobhouse, Day 3. (A surprising visit) Read More »
3/22/19: Building Summary: Today I started off by unpacking the bathroom vent fan from its box to see how I
Wiring Jacobhouse, Day 2. Read More »
(Above): A computer-rendered ‘oil painting’ of an image I took on my way to Jacobhouse this morning. Real image below.
Wiring Jacobhouse, Day 1. Read More »
3/20/19: Building Summary: Today I glued red CPVC valves to all available stub-ups in Jacobhouse. This was followed by filling
Many mini-valves (and the 12-hour point). Read More »
Pictured above: An image taken mid-gluing. (The mess was cleaned up directly after.) 3/19/19: Building Summary: Today I connected the
Cabinets incoming, and (more)ange glue. Read More »
(Above: Me, peering through the freshly placed sewage stub-down.) 3/18/19: Building Summary: Today I glued together the PVC to CPVC
Exterior stub-up, unstubbed. Read More »
3/17/19: Building Summary: Last night and this morning (with Padre’s help), I planned for the ‘converter’ that will take water
The converter. (And midnight shenanigans) Read More »
3/16/19: Building Summary: Today I started off the morning by emailing Custom Service Hardware to ask after the specs of
Floor support finished. Read More »
3/15/19: Building Summary: Today I started off by hooking the length of waterline we laid yesterday to the well’s outlet.
Water in the Pipeline. Read More »