The shower drain (and frantic finagling).
6/16/19 (Above: An image that Padre captured while I was bent over the shower drain applying some silicone gasket maker. […]
The shower drain (and frantic finagling). Read More »
6/16/19 (Above: An image that Padre captured while I was bent over the shower drain applying some silicone gasket maker. […]
The shower drain (and frantic finagling). Read More »
6/15/19 (Above: The now fully closed-in Wall #6.) Building Summary: Today I started off by trimming away the excess spray
Another hole (and lazy bovines). Read More »
6/14/19 (Above: The liberally spray-foamed Wall #6. I don’t think there will be many bugs getting in that way.) Building
Sealing Wall #6 (and foam eruptions). Read More »
6/13/19 (Above: Padre and Jacob reflected in the fully caulked sliding glass door.) Building Summary: Today I did not get
Caulking Wall #6, Day 2 (and more rain). Read More »
6/12/19 (Above: The almost fully caulked Wall #6.) Building Summary: Today I caulked almost the entire exterior of Wall #6.
Caulking Wall #6 (and quickly). Read More »
6/11/19 (Above: The now fully-trimmed Wall #6.) Building Summary: Today I started off by re-setting up the under-oak worktable, and
All trimmed up (and ready for the caulk-king). Read More »
6/10/19 (Above: Me being [unknowingly] photographed putting up a PVC trim-board.) Building Summary: Today I began installing PVC trim boards
Trimming Wall #6 (And a 2:40 PM Update) Read More »
6/9/19 (Above: Cows having a lazy Sunday morning beneath a stormy sky.) Commentary: Freekend, Day 2. Need I write more?
Freekend 2, Day 2 (and some fungi). Read More »
6/8/19 (Above: Cows enjoying their own freekend… Oh wait, that’s every day.) Commentary: It has been a relaxing and quite
Second Freekend (Day 1). Read More »
6/7/19 (Above: Jacobhouse to the left. Bee-hole to the right. Jacob and Wag to the far right in the background.)
Jacobhouse from above (and the bee-hole). Read More »